FOR IMMEDIATE
RELEASE
CONTACT: Katie Chimenti, 281-326-3343
Nancy Edmonson 281-471-4567
December 11, 2002
Spillman's Island Beats Bayport
New road construction, railroad spurs, and
other special requirements would produce significantly higher costs for
taxpayers if the Port of Houston Authority undertook container port development
at Bayport rather than at Spillman's Island, according to a newly released
analysis of the two sites. This conflicts directly with Port claims that that
the Spillman's Island alternative site is not an economic proposition.
Transportation analyst Nancy Edmonson recently compared the cost factors
unique to Bayport and to Spillman's Island. Using projections supplied by the
Port of Houston Authority itself, she identified more than $209 million in extra
costs to taxpayers if a container port were developed at Bayport. Costs unique
to Spillman's Island were much lower. Her analysis was conducted for the
Galveston Bay Conservation and Preservation Association, and the full report can
be viewed on the GBCPA website at
www.gbcpa.org.
The largest single set of extra costs at Bayport, almost $117 million,
would be for roadway work needed to accommodate an additional 5,000 trucks per
day on Highway 146. This amount involves intersection upgrades and does not
include improvements likely to be needed on the main stem of Highway 146; such
work would mean yet further costs, Edmonson notes.
The next largest amount is for new railroad lines--more than $60 million.
Spillman's Island, by contrast, would need little expenditure on rail and
roadways because it adjoins the existing container port at Barbour's Cut, where
significant public funds have already been invested in the infrastructure.
"While the tracks south to Bayport are single tracks, the lines to
Barbour's Cut were double-tracked a few years ago and could serve Spillman's
Island," Edmonson notes. On the highways, she says, "Truck traffic from
Spillman's Island would have direct access to SH 225, to which significant
capacity was added about five years ago, while truck traffic from Bayport would
travel on the already overburdened SH 146."
The third major category of extra costs at Bayport involves nearly $25
million in mitigation required because Bayport is so close to residential areas,
and because the Port would have to compensate for losses of coastal prairie and
wetland habitat. Finally, building a mega-container port at Bayport involves
purchasing of five sizable parcels of land, costing nearly $5 million. And
ownership of these lands by the Port, which pays no property tax, would mean at
least $2.6 million in lost tax revenue to Harris County, local cities, and the
Clear Creek Independent School District.
In contrast, Spillman's Island is an active dredge spoil site directly
fronting the Houston Ship Channel. It is remote from residential areas, reducing
impacts on surrounding communities. Building on dredge spoil would mean no
impacts on environmentally sensitive wetland and upland habitats, says Edmonson
in her report. Thus developing a container port at Spillman's Island would at
once increase efficiencies for the Port and avoid the complex mitigation
required at Bayport.
Despite these factors, the Port rejected Spillman's Island as an
alternative early on, claiming that the cost of stabilizing the site would be
$600,000 per acre. More recently, in an October 2002 letter to State
Representative John Davis, the Port has dropped its estimates to a range of
$297,000 to $428,000 per acre. For comparison, Edmonson notes that developers of
a container terminal at Shoal Point in Texas City--also on an active dredge
spoil site--have projected stabilization costs at only $90,000 per acre.
The acreage is also open to question. As proposed, the Bayport facility
would occupy more than 1,000 acres. But a container port planned for Texas City
covers 500 acres, and Seattle has recently opened a major container terminal on
only 200 acres. Both the Texas City and Seattle projects are designed for almost
the same throughput of cargo containers as at Bayport. Edmonson points out that
one reason for the 1,000-acre footprint in the Bayport proposal is inclusion of
a cruise terminal, and she challenges this in the report.
"There is no reason that a cruise terminal--if needed at all--must or even
should be built adjacent to the container terminal. In fact, Ricardo Fernandez
of Indigo Service Corporation--a nationally recognized cruise terminal and port
consultant--argues that cruise and container facilities should not be co-located
due to national security concerns," said Edmonson.
Further, the Port has indicated that about 100 acres of Spillman's Island
would not need stabilization. The Port assumed in a September 2002 letter to
John Davis that only 888 acres on Spillman's Island would need to be stabilized
for a 1,000-acre terminal. Edmonson therefore projected the Spillman's Island
stabilization costs for 400 acres--a container port with no cruise terminal and
covering 500 acres, as at Shoal Point, of which 100 acres would not need
stabilization work.
At the Port's current maximum estimate of $428,000 an acre, it would cost
$171 million to stabilize 400 acres of Spillman's Island. This is substantially
less than the $209 million in known additional costs at Bayport. At the Port's
lower-end estimate of $297,000 an acre, the cost of stabilizing 400 acres on
Spillman's Island would drop to $148.5 million. And if costs approach the
$90,000 per acre envisioned at Shoal Point, the cost of stabilizing Spillman's
Island would drop below $100 million.
--30--
Galveston Bay Conservation and Preservation Association
P.O. Box 323, Seabrook, Texas 77586
Phone: 281-326-3343
Website: www.gbcpa.org
E-mail: gbcpa@gbcpa.org